Plan to Transition from Routing Strategies to Business Hours
Some customers who have been on Webex Contact Center for some time may still be leveraging Routing Strategies (RSs) instead of the newer feature of Business Hours (BH). Here are some simple ways to transition from RSs to BH node.
Routing Strategy Review and Conversion
First review your routing strategies and identify the hours of operation for the Entry Points the associated RSs
Document your hours of operation in a document or spreadsheet similar to the attached
Don’t forget to review your Global Strategies to identify any overrides
Analyze your spreadsheet to identify potential groupings for Business Hours creation
Convert the RS information to a format that can be uploaded to Business Hours in Control Hub
Identify all Holiday routing and Override routing from normal RSs and Global RSs
Download the Business Hours template under Bulk Operations
Complete the Business Hours template spreadsheet and upload in Bulk Operations, including Holidays and Overrides
Flow Adjustment with Business Hours
There are two primary ways of moving to Business Hours nodes in your flows:
Add BH node into existing flows
Create BH flow in front of existing flows
The option you choose will largely depend on how complicated your flows are, and how proficient you are in developing flows.
Existing Flows
Using the documented RSs information, make a copy of all the flows associated with the EPs - these copies will be used to develop and test the Business Hours conversion outside of your production environment
In the copied flow, add the Business Hours node - typically it will be placed at the beginning of the flow
Add additional routing required for after hours, holiday, and override outputs from the BH node.
BH Flow in Front
Create a new flow
Add the BH node
Connect the business hours output to a GoTo node and reference the existing production flow
Connect the afterhours, holiday, and override outputs to the appropriate flows using GoTo nodes
If afterhours, holiday, and override flows do not exist, you can either create separate flows for each, or create the routing directly in the BH flow
Testing
In either creation scenario, testing your flows are key to a seamless and painless migration
Use a test number and test Entry Point
Associate the BH flow or copied production flow to the EP
Test the flows and make adjustments as needed
Go-Live
When you are ready to go live with your BH flow migration, confirm again you have tested all use cases for your business hours, afterhours, holiday, and override experiences
Determine a date to conduct migration activities
After hours is typically best practice for executing a migration
BH Flow Go Live
When ready to go live, simply go into each EP and change the Flow to the new production flow you created
Selec the “Live” version of the flow you published
Copied Flow Go Live
When ready to go live, simply go into each EP and change the Flow to the new production flow you created
Selec the “Live” version of the flow you published
Test each production change to validate functionality
CONGRATULATIONS! You did it! You have migrated from Routing Strategies to Flows!